Effect of Equipment Placement in a Flameproof Enclosure

Underground » Detection and Prevention of Fires and Explosions

Published: May 08Project Number: C13024

Get ReportAuthor: Ray Davis, James Birch, Ashraf Chowdhury, Bipin Parmar, David Soady | Simtars

The main purpose of this research was to simplify the process of pressure testing flameproof enclosures to allow for some degree of flexibility in the layout of internal components without the need for retesting. Because of the cost and time spent in the testing of a flameproof enclosure, manufacturers are constantly seeking to gain flexibility with their product.

Present testing of flameproof enclosures in accordance with AS/NZS 60079.1:2005 determines the pressures to which the enclosure may be subjected in the event of an internal ignition. Simtars is involved in testing and certification of flameproof enclosures and is one of only two testing stations in Australia accredited to undertake flameproof testing. The standard covering this testing leaves it to the discretion of the testing authority to ensure they find the highest explosion pressure possible in an enclosure.

The objective of the project was to investigate the effect of equipment placement within a flameproof enclosure and define limitations on such placement. By providing guidelines in regard to the limitations within which component placement can be changed or additional equipment included, the whole process of testing flameproof enclosures will be simplified.

Testing was carried out using cubic and elongated enclosures and gave results that varied depending on whether the components were in block form or thin plate form (i.e. mounting plate). This meant that the limitations required to avoid high pressures developing in the enclosures were different to cover both situations.

To satisfy testing to Clause 15 of AS/NZS 60079:1:2005 and be able to ensure that testing the enclosure empty represents the most severe conditions for explosion pressure development, the following limitations had to be applied. The apparatus within the enclosure may be placed in any arrangement, provided that an area of at least 10% of each cross-sectional area remains free to permit an unimpeded gas flow and, therefore, unrestricted development of an explosion. Separate relief areas may be combined provided that each area has a minimum dimension in any direction of 20 mm. However if a thin mounting plate is used it must provide an area of at least 30% of each cross-sectional area free to permit unimpeded gas flow, and , therefore the unrestricted development of an explosion.

Some limitations had to be placed on the enclosures covered by this finding due to the limited testing undertaken. Enclosures are limited to Group I application only and they are to be of basically simple geometry of only square or rectangular cross-section and no major dimension shall exceed any other major dimension by more than 3:1 and shall have an internal volume when empty no greater than 0.5 cubic metres.

These limitations do not preclude existing limitations which apply due to other requirements of the standard, AS/NZS 60079.0:2005 and AS/NZS 60079.1:2005.

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C34019Longwall Bretby Cable Handling Monitoring With Fibre Optics

This project examined the potential of using fibre optic sensing tec...

C27049Mine Machine Radar Sensor Integration

The aim of this project was to develop an integrated radar sensor an...

C29007Innovative Coal Burst System To Investigate The Influence Of Confinement Loss And Pre-Conditioning On Coal Burst Mechanism

The challenges associated with designing and operating a safe and pr...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C33035High Water Recovery, Low Cost Desalination Using PV-Powered Membrane Capacitive Deionisation (Mcdi)

Capacitive deionization is a robust, energy efficient and cost effec...

C28035Topsoil Deficits In Site Rehabilitation Accelerated Transformation Of Spoils To Functional Soils

The incorporation of commercial biological amendments (compost, worm...

C34036Tyre Handler Testing Rig Stage 2: Lifting Trials

Tyre handling is a major source of risk in surface mining operations...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement

This multi‐phase project is concerned with the mitigation of m...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook